A) 27 days
B) 54 days
C) 56 days
D) 68 days
(A’s 1 day’s work) : (B’s 1 day’s work)
=2:1(A+B)‘s 1 day’s work=118∴A’s 1 day’s work=(118×23)=127=2:1(A+B)’s 1 day’s work=118∴A’s 1 day’s work=(118×23)=127
Hence, A alone can finish the work in 27 days.