C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?

A. 10 days
B. 12 days
C. 8 days
D. 9 days

Leave a Comment

Your email address will not be published. Required fields are marked *

%d bloggers like this: