P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work? February 24, 2021 / By Preparation Point / Basic Maths Mcqs Share on WhatsApp Share on Facebook Share on Twitter Share on LinkedInA. 8 B. 6 C. 4 D. 2 Share this:TwitterFacebookMoreTelegramWhatsAppLike this:Like Loading... Related Share on WhatsApp Share on Facebook Share on Twitter Share on LinkedIn