60 men can do a work in 40 days. How long will it take 40 men to complete the same work?

A) 30 days

B) 29 days

C) 23 days

C) 60 days

Solution by Preparation Point

If 60 men can finish a work in 40 days then 40 men can finish the work in 60 days.

Men × days = men1 × days1

60 × 40 = 40 × x

x = 60 days

 